It has been a slow start this year with a late spring and all the rain, however with the weather now on our side, construction is moving along well at a good pace.

The water main is installed throughout Phase 1 and the pump stations for the water system are delivered on site with installation starting this week.

The “shallow utility” (BC Hydro, Telus, Shaw & Fortis Gas) work is underway with the expectation of paving start by month end. 

Final lot staking for registration purposes its underway with the buyers of the 7 lots sold under contract ready to take possession soon.